On August 10th, along with the smooth entry of the equipment into the site, the Banana Flour Production Line Project Delivery Launching Ceremony was successfully held at the installation site of the Dole plant in the Philippines. The project team of Dole banana flour production line Philippines witnessed this important moment together.
Previously, our installation team communicated with the Dole project team about the project's safety regulations, schedule, and installation program, and confirmed the installation materials and tools, as well as erected a fence around the construction area and signed a safety responsibility letter with the installation team members.
On September 27, the project team organized the overall acceptance of the project, under the team members' professional installation ability, exquisite debugging technology, and responsible plan control, the project team has completed the installation, debugging, trial production, training and other node tasks within the pre-scheduled period. Successfully passed the acceptance.